What Rock Breaking Costs in New Brunswick
$200 to $300 an hour for a breaker
One national guide read in September 2026 (thin); large machines run higher. Blasting has no usable published price.
Reviewed 2026-09-28 · how we set these ranges
Nobody can price rock they have not seen, so the plan for rock is really a plan for the contract: how it is found, how it is counted and who may break it.
1 The pieces of the price
Rock, if it turns up
By the hour with a hydraulic breaker, or as a quoted extra
$200 to $300 an hour for a breaker (thin: one guide; large machines run higher)
Machine time
By the hour, with operator
Mini $65 to $150 an hour · standard $150 to $250 an hour
Trucking the spoil
Per load or per truck hour
Too few published prices to average: ask for the load count and truck size in writing
Blasting
Quoted by the blasting contractor
No usable published price
2 What's under your yard
The things nobody can see until the bucket goes in, and what to do about each before it does.
-
Rock
We found no public source on how deep rock sits under any New Brunswick town, so nobody can promise a rock-free lot.
Before the dig: Get the rock clause in writing before the dig: how it is found, how the breaker time is logged and what it costs per hour.
-
Buried lines
Gas, power, cable and old private lines can sit anywhere in a yard. NB Power says its lines can be buried as little as one foot down.
Before the dig: The contractor must have utilities located before digging (WorkSafeNB). Ask to see both tickets: Info-Excavation (3 working days' notice, valid to the end date on the request) and NB Power (five business days, valid 60 days, NB Power lines only). Mark private lines yourself.
-
Who may blast
WorkSafeNB's Regulation 91-191 says a blasting operation must be run by a blaster with a certificate of qualification issued under the Apprenticeship and Occupational Certification Act. We found no provincial homeowner blasting permit and did not find town blasting by-laws.
Before the dig: Ask your municipality before anyone plans a blast, and ask to see the blaster's certificate.
-
A brook, lake or wetland nearby
Any clearing, digging, fill or machine work within 30 metres of a watercourse or wetland needs a provincial WAWA permit first. The 30 metres is measured from the top of the bank, on the ground.
Before the dig: Measure before you book the machine. The landowner usually applies; a single alteration is $25.
3 Before the first bucket
Tick them off as you go. Nothing here is saved or sent anywhere.
4 Rules by place for this job
- Every town
- We found no provincial homeowner blasting permit and did not search municipal blasting by-laws: ask your municipality.
- Anywhere else
- We found no excavation-specific rule for Dieppe, Sussex, Miramichi or other towns: ask your municipality or Regional Service Commission before the machine arrives.
What the written quote should name
- What counts as rock for billing
- The breaker rate and how hours are logged
- Whether blasting is possible and who would do it
- Where broken rock goes, or whether it stays as fill
- A written notice before the breaker starts
More on the work itself: Rock Breaking & Removal
Questions people ask
Can they tell before digging if my lot has rock?
Not from any public source. Test holes can show what is there before you sign a fixed price.
Who is allowed to blast?
Only a blaster with a certificate of qualification under the Apprenticeship and Occupational Certification Act, per WorkSafeNB's regulation.
Is a trench in solid rock safer?
A trench cut in solid rock is one of the exceptions to WorkSafeNB's shoring rule; rock excavations deeper than 1.8 metres carry an extra rule.
Want this done at your place?
Tell us what needs digging and we'll pass it to local New Brunswick excavation contractors for a written quote. We send it out to local contractors for you. Free, no pressure.
Plan another job
- Foundation dig$7,500 to $30,000 for a whole-house dig
- Water or sewer trenchMini $65 to $150 · standard $150 to $250 an hour
- Septic dig$3,000 to $12,000 for the excavation
- Lot clearing and gradingMini $65 to $150 · standard $150 to $250 an hour
- Driveway dig and base$1,500 to $5,000 for excavation and base
- Weeping tile and drainage digMini $65 to $150 · standard $150 to $250 an hour
- Backfill and haul-awayCrushed stone $40 to $75 per m³